Silver Lake
Railroad

Offering Train Rides
BY DONATION

The Railroad Report

SLRR Washout News / Update

Posted on November 22, 2010 at 11:58 PM

SLRR Washout Update


Thanks to the volunteers who helped fill the washout and workers from the state our washout is now filled. 


On Monday and Tuesday 11-22 and 11-23, Two state employees, a member of the snowmobile club and our operations manager Bruce Stuart worked to fill the washout on our line.

 


Here's how it happened- After we close for the season, we rarely do track and line inspections. The "busy beavers" got to work very quickly, and nearly completely clogged our 5*7 ft. culvert. One of the passing rain storms raised the level of the beaver pond to over the culvert ceiling and the water pushed on the soft sand that was underneath the ballast. (soft sand was in that location because that section of track had laid dormant and washed-out for nearly 15 years, and the sand was brought ashore. (we filled it in 2008 ) The State has cleared their culvert (line is owned by State of NH- we only own nearly 1000 feet of track), and provided us with fill and labor. We completed fixing this washout on tuesday 11-23-10. Picture of the filled washout are linked below along with captions written by operations manager Bruce Stuart and I!



Thanks to all who helped out on Monday and Tuesday!


Photos: credit to Joe Sheehan


Joe Sheehan Loads The First of Many

It took a joint effort by the SLRR, NH Bureau of Trails, Ossipee Valley Snowmobile Club, and Colemans Sand and Gravel to accomplish this washout fill.


 

Workers Starting to fill the Washout

 


SLRR Operations Manager Bruce Stuart and Trails Bureau member Josh utilize the 1931 Anthony bodied hydraulic dump cart to start filling in the washed area.


 

Fill Starts Taking Shape


 

 

The fifth load of a fifty three total loads.

Positioning Dump Car Over Fill

 

Rail was jacked and four by four pillars were cut, sized, and placed on the eastern side of the track for support.

Continued Dumping of Fill

The heaviest rains and cold temperatures prevailed on monday, but the fill continued throughout the day.

 

 


 

Frank Spreads Gravel

 

Trails Bureau member Frank spreads fill through the washout. It took two eleven hour- four man work days to complete the project.


 

Support Pillars Used On Every Other Tie

 

The washout encompassed fifty linear feet by three feet of depth and ten feet of width. Pillars were needed in order to support the work train. (Blue A6 and Dump Car)


 

Fill Arrives Monday Morning

 

A total of 110 yards of gravel were needed to fill the washout. A Colemans truck delivered the fill to boulder Rd on monday morning at 9AM. Colemans input toward this project was essential.


 

Work Train Shuttles Gravel

 

 

This was one of fifty-three total loads. The Washout was approximately three quarters of a mile south of Boulder Road around MP B128.5. We were able to pick up the load, shuttle it, dump it, and spread it at approximately three loads an hour.

Loaded Dump Car

Without this piece of equipment, projects such as this one would be extremely difficult to accomplish.

 

 

Unloading Dump Car

 

 

Starting to build out the shoulder.

 



-Will Scopa

SLRR Volunteer

Categories: 2010 Season

Post a Comment

Oops!

Oops, you forgot something.

Oops!

The words you entered did not match the given text. Please try again.

You must be a member to comment on this page. Sign In or Register

3 Comments

Reply PokkerJoe
07:08 PM on December 04, 2010 
Looking forward to working with SLRR in the summer.
Reply slrr1
08:43 AM on December 04, 2010 
PokkerJoe says...
Glad I could help out.


Thanks Joe, it looks good!
Reply PokkerJoe
06:16 PM on December 03, 2010 
Glad I could help out.

Upcoming Events

No upcoming events

Recent Videos

301 views - 0 comments
777 views - 0 comments
1037 views - 0 comments
925 views - 2 comments